Flow Enablement Services (Magic xpi 4.13)
Flow Enablement services contain the following parameter. (The parameters in bold are mandatory):
|
|
Activation Type
|
Select one of the following flow activation types from the drop-down list:
-
Always (default): The flow will always be enabled.
-
Weekly: The flow will be enabled on a weekly basis. Select the check box(es) to define which day(s) in a week the flow will be enabled. Click next to the Flow Enablement Times parameter to open the Enablement Time Ranges list. Here, you enter the start and end times for when you want the flow to be enabled.
-
Monthly: The flow will be enabled on a monthly basis. Select the check box(es) to define which month(s) in a year the flow will be enabled. Click next to the Flow Enablement Dates parameter to open the Select Dates dialog box. Here, you enter the specific dates in a month for when you want the flow to be enabled. Click next to the Flow Enablement Times parameter to open the Enablement Time Ranges list. Here, you enter the start and end times for when you want the flow to be enabled.
|
Holiday Calendar
|
If you do not want to activate the flow on a given day, select one of the Calendar entries from the drop-down list.
The list of calendars will be populated based on the list of calendars defined in the Calendars section.
Any changes done to the Calendars are effective immediate, for all running projects.
|
This is not applicable if the Activation Type (above) is configured as Always.
|
(Since version: 4.13)
|